Hotel Chmielna 78 Gdańsk is being built. Work is in full swing on the construction site!

Hotel Chmielna 78 Gdańsk is being built. Work is in full swing on the construction site!

Granary Island has been a meeting place for merchants from all over the world for centuries. Thanks to Marvipol Development and the commitment of the Adamietz team, a new four-star Hotel Chmielna 78 is being built in this historic area. We have completed two important milestones:

  • Execution of the ground slab (foundation) together with underfloor drainage and installations: lightning protection and earthing systems,
  • Completion of level “0” in terms of structure – including the garage and the ceiling above it.

We have also successfully completed earthworks, geotechnical works and excavation dewatering. Currently:

  • We are carrying out reinforced concrete works on the first floor and finishing the ceiling above the ground floor in one section of the building,
  • In another section, reinforced concrete works on the ground floor are still ongoing,
  • In the garage, we have started building walls for technical rooms and are preparing for the installation of heating substation equipment.

The coming months will be full of new challenges – subsequent stages will include sanitary and electrical installation works. Follow our progress – we will share further updates soon! The investment is being carried out by the Gdańsk branch of Adamietz.

Construction Manager: Mariusz Sawicki
Project Manager: Adam Borowiec
Branch Director: Krzysztof Rytlewski